Is it possible that system creates a project version automatically on change of system / user status at WBS level (not Proj Defn)?

Comments / suggestions please.

TIA

Santosh

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear,

you should change the status which you have defiened in version profile manually or automatically .

you can defined meany status in this version.

Regards.

Former Member
0 Kudos

Hi,

Yes, it is possible.In the version profile, you specify the objects to be included in a project version, (for example, WBS elements, activities, production resources/tools, or costs) and when the project version should be created. In the version profile, you can enter as many user and/or system statuses as you want for creating a project version.

http://help.sap.com/erp2005_ehp_03/helpdata/EN/ee/41f1c846ee11d189470000e829fbbd/frameset.htm

Hope it will help you.

Regards,

Former Member
0 Kudos

A project version does get created automatically when Project Defination Status changes.

But can this automatic creation be done when status of only one WBS below a Project Defination changes.

I have define a version profile with required user status and ahve assigned the same to the project profile. Is there something I am missing?

Thanks.

Santosh.

Former Member
0 Kudos

Dear,

yes its possible to create a project version automatically

by changing of s/s or user status .

By the config of project version and select the S/S status from that you want to create the project version by changing s/s status,define in version profile.

regards.