Cross Period Lot sizing

Hello everybody,

We have a scenario wherein we are running the SNP optimizer in daily buckets. However the production time for the FG is exceeding one day. We observed that the optimizer does not generate any planned order.

We then activated the cross period lot sizing in the resource master and rerun the optimizer. Now the optimizer run is terminated and cross period lot sizing is not considered.

However when we run in the weekly bucket, the planned orders are created.

has anyone come across a similar scenario. I would like to know if there are any additional settings required to use cross period lot sizing. Is there any relation between the production time and the

Regards,

Kedar Agarkar