Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Shiftwise Production order

Hi Guys,

I am working in MTO. I have a FG material which is produced in 15 days. My plant works for 3 shifts. We have planned order generated by MRP run using which we create the production order.

My problem is i want to create production order shiftwise And i want to create this using planned order which should be generated after MRP run.

Is this possible.

Regards

Samarth