Factory Calendar has 5 working days in Route but Delivery date on Sunday?

Hi All,

I have created a PO for a country XX to a Country YY

I have defined a Route from XX to YY with a transit time of 5 days and also factory calendar of XX as calendar.

When i create a PO from XX to YY , in Delivery Schedule of the PO , i see the commited date of delivery considers Sunday and Saturday also.

But the business does not want to conisder sundays and saturdays, How does the commited date determined in PO?

The factory calendar of XX does not consider Sat and sunday but the Confirmed delivery date shows Sunday ?

For example if delievry date: is 19 Sep

Transit time is: 5 days

Confirmed Delivery date in PO is : 14th Sep( Sunday)

But actual date should be :12th Sep ( Friday)

Please advice!!

Thanks,

Kumar

Former Member