Factory Calendar has 5 working days in Route but Delivery date on Sunday?

Former Member
0 Kudos

Hi All,

I have created a PO for a country XX to a Country YY

I have defined a Route from XX to YY with a transit time of 5 days and also factory calendar of XX as calendar.

When i create a PO from XX to YY , in Delivery Schedule of the PO , i see the commited date of delivery considers Sunday and Saturday also.

But the business does not want to conisder sundays and saturdays, How does the commited date determined in PO?

The factory calendar of XX does not consider Sat and sunday but the Confirmed delivery date shows Sunday ?

For example if delievry date: is 19 Sep

Transit time is: 5 days

Confirmed Delivery date in PO is : 14th Sep( Sunday)

But actual date should be :12th Sep ( Friday)

Please advice!!

Thanks,

Kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184555
Active Contributor
0 Kudos

Hi

For inward movement of goods the calendar assigned to the shipping point also will be considered. If delivery can be processed on sat and sun as per the calendar in shipping point, then it will determine so.

For outbound deliveries, the customer unloading data is considered for determining the dates. If unloading is not accepted on sat and sun, then it postpones the delivery date to the next acceptable date.

Thanks,

Ravi

Former Member
0 Kudos

Hi,

Pl. check whether same factory calendar assigned in OVLZ.

Thanks

Krishna.