Hi Friends,
We are facing one BOM related problem,
We have two Material BOMs(1035NA &1035 NB) lost month we are deleted TYRE component from BOM (Confirmed from CS03) but while doing Standard cost estimation (CK11N) system is capturing the tyre cost.
But the same is correct in case of 1035NB(System doesnu2019t capture tyre cost).
Can you help in understanding n what could be the reason for same.
Thanks & Regards
Purna
Dear Purna,
Check out this,
If you are using ECN - Engineering Change number for changing the BOM's,check its valid from date (for
the Change Number).Becuase if you are using a Change number which's valid from 25.09.2008,then if you
use this Change number for deleting or making any BOM changes,then the changes made will be effective
from 25.09.2008,even if you have made it today.
So in CK11N,if the Quantity structure date,Valuation date & costing date from if its going to be between
from today's date to 24.09.2008,the system wont consider the changes that are made.
Moreover if you are using a Change number with release key,then check whether the release key is set for
the change number in CC03.
Take the help of your PP team and try to solve the issue.
Revert back if you need any further assistance.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
While running CK11n check the Quantity structure date...if its correct date (the date after you have changed the bom).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.