Dear PM Gurus

can anybody please tell me in detailed steps how i can make settings in spro for following problem :

I want to make outline agreement mandatory while i m making maint. order only with control key PM03 (external services).

Thanks in adavance

regards

vineet

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

you can achieve in field selection for PM/CS order operation .in T code OIOPD ,in that select influencing and specify control key PM03 and make the outline agreement has mandatory

regards

thyagarajan

vineet_sharma4
Participant
0 Kudos

dear mr. tyag

i m already doing that but the problem is coming when i take control key PM01 even then it is asking for outline agreement no.

regards

vineet

former_member187991
Active Contributor
0 Kudos

hi

i think you have not specified in influencing field ,type T code OIOPD,in that screen select the INFLUENCING button ,as soon as you press that you can see 2 fields order type and control key ,double click on control key and specify PM03 and make outline agreement has required entry

regards

thyagarajan

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

vineet,

Have a look [here|;

PeteA