on 09-11-2008 5:22 AM
Dear PM Gurus
can anybody please tell me in detailed steps how i can make settings in spro for following problem :
I want to make outline agreement mandatory while i m making maint. order only with control key PM03 (external services).
Thanks in adavance
regards
vineet
hi
you can achieve in field selection for PM/CS order operation .in T code OIOPD ,in that select influencing and specify control key PM03 and make the outline agreement has mandatory
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
i think you have not specified in influencing field ,type T code OIOPD,in that screen select the INFLUENCING button ,as soon as you press that you can see 2 fields order type and control key ,double click on control key and specify PM03 and make outline agreement has required entry
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.