SC order to create commitment in CJ30 / CJI5

Hello SRM Guru's,

Extended Clasic Scenario

Business Process: SC is ordered with budget avalibility control active in ECC is created with a WBS element having budget assigned to it , this SC will go for approval>>> PO will be created in EBP, will go for approval .....PO will get replicated in ECC.

We want to create commitment in CJ30 for that WBS element as soon as SC is ordered and not wait untill SC is approved.

We dont want to wait until PO gets replicated and PO creates comittment.

How can we go ahead on this? Can BBPCO idoc handle this if i use this in new process code and add this in ALE Inbound/Outbound?

Has anyone did this for create , change, delete of SC.

Thanks,

Anil

Former Member
replied

Hi,

It is not standard solution but consulting service is available.

Please check the note 900825 Shopping cart commitment.

[https://service.sap.com/sap/support/notes/900825|https://service.sap.com/sap/support/notes/900825]

Regards,

Masa