hi guys
i want to took Planing horizon for 100 days ,but few raw materials wil take time procure 180 days ,so the MRP only will take account into within 100 days ,so shall i change my planing horizon
thanx in adavnce
Hello Karthi,
I think you need not change your planning Horizon period.As Rajesha said, it is only for select the requirement during MRP.
Based the planned delivery time system will schedule and will create procurement proposal for raw material.
Regards
Pradeep Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please understand that planning horizon is to consider the requirements.
example - for a RM there is a requirement as below
30.12.2008 - 10 qty
30.11.2008 - 10 qty
30.10.2008 - 10 qty
30.09.2008 - 10 qty
If your planning horizon is 100, then system will consider the requirements which fall below the date today + 100 days = 22.12.2008. i.e. after running MRP
30.12.2008 - 10 qty
No recipet for above requirement as it is bwyond 100 days.
30.11.2008 - 10 qty
Planed order for 1o qty
30.10.2008 - 10 qty
Planed order for 1o qty
30.09.2008 - 10 qty
Planed order for 1o qty
If your planning horizon is 180, then system will consider the requirements which fall below the date today + 180 days = 22.06.2008. i.e. after running MRP
30.12.2008 - 10 qty
Planed order for 1o qty
30.11.2008 - 10 qty
Planed order for 1o qty
30.10.2008 - 10 qty
Planed order for 1o qty
30.09.2008 - 10 qty
Planed order for 1o qty
I hope you are clear about the concept.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.