Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

CTS+ for SLD objects between 2 different SLD's ?

Hi,

Is anyone using CTS+ to transport SLD objects between 2 SLD's ?

I'm asking because I did not find much information about this particular subject.

We have 3 PI 7.1 SPS6 systems (DEV-QA-PRD) and plan on using 2 SLD's (1 design-time and 1 runtime).

The SLD's are 7.0 SPS15.

Our DEV-QA PI systems are using the design-time SLD, the PRD PI system is using the runtime SLD.

As per the documentation (SLD planning guide, page 21), CTS+ should be able to transport Business systems, SWC, products, etc

I did all the configuration mentionned in the document "How to...Configure enhanced CTS for Sap Netweaver Process Integration SPS06" but nothing is mentionned regarding the SLD objects.

All my PI objects (Integration Directory, Integration repository) are transported between the PI systems but the SWC/products do not get transported in my Runtime SLD. (even with the parameter "DEPLOY_SLD_URL" in TMS for my PRD system).

Any ideas what I am missing ?

P.S. Please answer with CTS+ related solutions, not export/import or CMS.

Thank you !!

Not what you were looking for? View more on this topic or Ask a question