Hi All,
I am in a critical situation , so could you please guide me to solve this issue will be grateful.
My issue is
Sales orders are creating a planned orders for Top level materials [Material A] but it's not creating a requirements for low level item [Material B].
Low level item is buy part so , I am looking for PR needs to be created after MRP, but in MD04 nothing is visible.
So please help how to get the demand on MD04 for low level items.
Thanks in Advance.
Hello Madhan,
Please check with below points.
1.MRP type of low level material = PD
2. Stock of low level material
3.BOM validity of Low level material.
5.Any Exception message for Header material planned order
6.Is it Multi level planning (Md01 or MD02)
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
What is the planning strategy of the material.
Are you running MRP after sales order creation?
If yes what is the transaction you are using?
regards,
Ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.