Hi PP Gurus,

We are having one SFG containing some raw materials having Base UoM KG (kilogram) and alternate UoM PC (pieces). The BOM of SFG having UoM as KG. At the same time it is getting used in FG but having UoM as PC. We created SFG with Base UoM KG and alternate UoM is PC and gave proper conversion in material master record. But when we're trying to create BOM for FG and putting SFG as BOM item with UoM as PC system is giving error message.

It it possible in SAP?

Please make your valuable remarks.

Thanks & Regards,

Abu Arbab

replied

hi

you should have to maintained issue unit in material master of SFG is PC in plant data/ stora 1 tab of material master. then system will not give you error.

please come back if have any query

Regards

Pravin