Material BOM with UoM.

Former Member
0 Kudos

Hi PP Gurus,

We are having one SFG containing some raw materials having Base UoM KG (kilogram) and alternate UoM PC (pieces). The BOM of SFG having UoM as KG. At the same time it is getting used in FG but having UoM as PC. We created SFG with Base UoM KG and alternate UoM is PC and gave proper conversion in material master record. But when we're trying to create BOM for FG and putting SFG as BOM item with UoM as PC system is giving error message.

It it possible in SAP?

Please make your valuable remarks.

Thanks & Regards,

Abu Arbab

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

you should have to maintained issue unit in material master of SFG is PC in plant data/ stora 1 tab of material master. then system will not give you error.

please come back if have any query

Regards

Pravin

Former Member
0 Kudos

Hi Pravin,

Thanks for your quick reply. The issue is resolved.

Thanks & Regards,

Abu Arbab

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello gurus,

I have a scenario where i have finish material with kg as UOM,for which BOM we have maintained UOM each.For routing also its reflecting kg.When i run MRP for finish material it will consider.My question is how it will affect for routing.

Regards,

sunil

Former Member
0 Kudos

Hi Sunil,

For material quantity calculations it will refer BOM, for activities like machine hour and labor hour calculation it will refer routing. MRP is based on material quantities and respective deliveries, hence it will refere only BOM UOM.

Regards,

Balaji NG