Hi MM Gurus,

Problem Description:Contracts are showing different planned delivery times than entered in MM02. Have not changed MM02 after contract was created. Causing problems with requisition dates. !

Can u guys suggest me.

Thanks,

Rahul

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member335885
Active Contributor
0 Kudos

HI,

Go to ME12 / ME13 and check the plant delivery time here also and see which one is been picked is it from material master or the inforecord.

Thanks & Regards,

Kiran

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Check whether it is picking Planned Delivery Time from Purchase Info Record.