Target Costs not appearing

0 Kudos

While going to cost analysis through CO03, I am not finding target costs, while actual cost and planned costs are all correct. In target cost column all components are zero for this material. This production aredr is in DLV status and the delivered qty is equal to the production order qty.

Please let me know why the target costs are not appearing for this material in the production order?

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

question is answered.

Former Member
0 Kudos

You need to do the variance calculation in KKS2, then when you save the variance, the target cost is calculated.