on 09-10-2008 2:26 PM
hi
for the LINE ID's, why should assign all cost element.
for WIP through gl it is posted.why should assign all cost element to line id's
thank you
sowmya
Dear Sowmya, The Line ids in the WIP configuration helps in capitalizing the costs of seperate groups. There shall be four to five line ids. Seperate line id for material, labour, overhead and revenue. If we need to capitalize only material and Labour, we can configure in this line id as 'Required to be capitalized' and for others, we need to enter in 'Not to be capitalized'. I hope that I have understood your query. If not let me know. Trust this helps much! Regards, Ashok SINGH