In MRP4 view, why and what to select in selection method? Please tell me what to give in case of ROH, HALB and FERT individually.

Regards,

Mohammad Arif.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member577912
Participant
0 Kudos

FOR ROH KEEP BLANK, FOR FERT & HALB IF U HAVE PRODUCTION VERSION, THEN SELECT 2 OR 3, IF U HAVE BOM MORE THAN 1 WITH DIFFERENT VALID DATE THEN TAKE 1.

MANISH

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

In the material master MRP 4 view there is one field in which you can mention that this material is not relevant to MRP planning, use this field for subcontracting material so that it will not be planned in MRP runs

BOM selection method. Produuction version Incase of FG and SFG.

Collective and individual indicator.

Regards,

R.Brahmankar

dhaval_choksi3
Active Contributor
0 Kudos

Hy Arif,

This field is more relevant to materials which are produced in house.

So this field is work for HALB / FERT and Identical value is 2 or 3 (selection by production version or selection is only by production version.)