Hi All,
I posted a schedule agreement to a particular G/L account,and found that the cost is not captured in budget report for the project.
This problem also exist for PR/PO/GR.
What could be the reason for this and how could it resolved.
Please help.
Reagrds,
Vishal
Hi,
I have checked for the tolerence limits . Its ++ (All Activity Groups).
Also the budget values are shown...
Now I want to know, what is this transcation CJEN & PSJ for ?
What is the purpose of using this transcation?
Thanks& Regards,
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in budgeting config check the business transactions for tolerance limit config to ++++
run cjen to update PSJ for your project
check if budgeted values are shown??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.