Hello Gurus,

What is JIT call Schedulign agreement in SAP??

Which document type d we use??

What are the settign generally we do for edi JIT SAs??

Regards

pratyush

Tags:
Former Member
Former Member replied

Hi,

Document type:

The standard document type used for Scheduling agreement related to jit is lzj.

What is JIT concept:

The Jit concept is the business do not need to maintain the stocks for production or manufacturing, where ever the quantity is required can order the required quantity just in time.

In sap the required quantities are received throuhg inbound idocs with dates and quatity.

For EDI JIT settings

OVAi, OVa9 and JITV master data ........if you need in detailed what these are you can post back.....