Hi experts,

i have created MTO scenario in PP

All the master data created( 1. material, 2.BOM,3.Work center,4.Routing) 5.Sales order created(VA01)

6.MRP Run (MD50)

checked planned order with md04

checked P.R with ME53n

7.production order with ref to sales order (CO08).

8. Production order confirmation (CO15)

parallel task MB1A.

9.Good receipt with mov. type 101 (MB31)

Please tell me whether these steps are correct or not

And at last i checked my stock by MB5B it showing no data, whether it will be the settings problem in stock seeing if so how to resolve this.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi

see here the flow

( 1. material, 2.BOM,3.Work center,4.Routing) 5.Sales order created(VA01)

6.MRP Run (MD50)

checked planned order with md04

checked P.R with ME53n

7.production order with ref to sales order (CO08).

when you run the MD50 system will give the planned order, against the planned order you convert to production order.

no need to go to CO08 to create teh production order agianst the sale order.

asn to see the stock go to MMBE , MB5B.

-ashok

Former Member
0 Kudos

Hi,

wheather u able to c stock through MMBE???

Former Member
0 Kudos

Hi

Steps seems to be correct. For stock, check MMBE or MB52. Also u can see in MD04.