on 09-10-2008 11:07 AM
Dear Experts.
I am satating below the scenario which is not working. MY Scenario is Plan Driven Procurement
If My PO is SRM Portal & in NEW status. If this PO is confirmed then COnfirmation is coming to R/3 System.
If after that I am changin MY PO in R/3 & sending the IDOC from R/3 . It is going to SRM but Not Reflecting in the SRM Properly. Like Suppose I have changed PO qty from 100 to 110 in R/3 System & sending the changes from R/3 to SRM through IDOC. PO status remains Confimed only on portal & Qty also remain same as 100.
This is the specific change which is not reflecting in the SRM portal.
So Pls suggest Me.
Thanks & Regards
Gautam khatree
Hello All ,
I am facing the same issue , Could you please let me know the resolution ?
Thanks !
Devesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Hope that your Job bbp_get_status_2 is running perfectly ?
This Job takes information from r/3 to ebp.
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Muthu,
My Job is running fine & giving the Spool Display as mentioned below.
_______________________________________________________________________________________
10.09.2008 Batch program for updating status information for SCs as of Rel. 3.0 1
'ld like
No Shopping Cart (REQUIREMENTS) Found with Status = Transferred
'
10.09.2008 Batch program for updating status information for SCs as of Rel. 3.0 2
On the basis of the data, no changes possible
'
The following RFC destinations were called:
RFC Destination: Call result:
________________________________________________________________________________________
I would also like to through more light... If I am archiving the PO from SRM Server & Resending the PO from R/3 to SRM .. Then it is working fine.. means after that i am confirming the PO Confirmation comes to R/3... Then Changing the PO in R/3 & sending changes to SRM PO is coming in In Process Status .....& changes are also get updated....
Pls Suggest...
when posting the issue on forum, please be quite clear about technical setup and business scenario so that others can help you well.
If I am not wrong yr tech scenairo is Classic and you are setting PDP SI (supplier integration) with MM-SUS.
Your issue is change order is not updated in SUS sytem.
First check whether the changed PO in MM is updated in SUS before GR/confirmation.
For this check outbound IDOC is originated from MM (WE05).
It is received in yr XI system.
outbound XML is created in XI (SXMB_MONI).
Inbound XML is received by SUS (SXMB_MONI).
BR
Dinesh
You are very true Dinesh.... Next Time Will take Care....
My Scenario is exactly, what you described ...........
This Error is in one Specific Order Change Scenario.... I am mentioning below the answer of your questions.
First check whether the changed PO in MM is updated in SUS before GR/confirmation.----Yes
For this check outbound IDOC is originated from MM (WE05).------Yes Checked in WE05 Idoc is fine..
It is received in yr XI system.----
Yes Change data are received perfectly in XI.
outbound XML is created in XI (SXMB_MONI).-------Yes
Inbound XML is received by SUS (SXMB_MONI).------Yes
This Change updation problem is only for the PO in New status at SUS -After Confirmation of PO- Confirmation comes to R/3---- After This if i am changing the PO then Changes are not updating in the Portal as PO --in Process.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.