Hi gurus

While carrying out availability check in sales order after entering material in line item, In the popup screen of availability control,confirmed qty is showing as 0 and delivery proposal showing as not possible. moreover the material qty has not been confirmed in schedule lines tab page in the line itam.

any body can help me ,what is the reason for qty not been confirmed? , any conifiguration is missing in this?.

correct replys will be rewarded.

Regards,

pavan.

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Problem has solved

Thankyou for the replys.

Regards,

pavan

Former Member
0 Kudos

Hi Pavan,

Can you please tell us that what is the date is showing in requested delivery date in sales order & what date in schedule line.

Regards

San

Former Member
0 Kudos

Hi,

It is showing same dates in the both places.

Regards,

pavan.

Shiva_Ram
Active Contributor
0 Kudos

Hi,

Check the field safety stock in MRP2 view of the material master.

If a value is filled, then remove the value or maintain stock in the plant more than the safety stock using MB1C transaction code.

Regards

Former Member
0 Kudos

Hi,

I have checked in MRP 2 view safty stock field is empty.

I will give you the Over view of MMBE

__Cl/CC/Plant/SLOC/Batch__-_Unrestricted use_-_Qality inspection_--_Reserved_

Plant 4970 0,000 0,000

Consignment stock 100 0,000 0,000

Storage Area 4370 0,000 0,000

Could you make it out of this what might be a reason?

Regards,

pavan.

Shiva_Ram
Active Contributor
0 Kudos

Hi,

May I know the plant number you are using in the sales order?

Former Member
0 Kudos

Hi,

Plant number is 1534.

regards,

pavan.

Shiva_Ram
Active Contributor
0 Kudos

Hi,

Use transaction MD04, enter the material and plant details.

Then in the first line (row) you can see available quantity. It should be displayed with positive quantities. If the system displays negative value means, there is no sufficient quantity in stock. Here you can also see any other orders or deliveries which are reserved with any quantities.

The same can be checked using transaction code CO09. Here the cumulative available to promise quantity can be viewed in the last column of the display.

Check the details and let me know.

Regards

Former Member
0 Kudos

Hi Shiva,

Problem has solved

Thankyou for your concern towards others.

Regards,

pavan

Former Member
0 Kudos

Thankyou for the replys,

what ever you told me i have followed and checked but no use ,still qty not been confirmedd.

still any thing is missing?

Regards,

pavan.

Lakshmipathi
Active Contributor
0 Kudos

Dear Pavan

Go to material master MRP3 view and ensure that you have maintained 01 or 02 against Availability check.

thanks

G. Lakshmipathi

Former Member
0 Kudos

it is showing as 02 aginst availability check in MRP 3 view material master.

regards,

pavan.

Lakshmipathi
Active Contributor
0 Kudos

Dear Pavan

I forget to ask previously whether for your schedule line category, have you checked the field "Availability" ?? Check in VOV6.

thanks

G. Lakshmipathi

Former Member
0 Kudos

In vov6 i have checked three

availability check,TOR,Productallocation.

Regards,

pavan.

Former Member
0 Kudos

Hi there,

In scheduled line catg, try by not selecting the Product Allocation field. It should work. Just have availability check & TOR.

Regards,

Sivanand

Former Member
0 Kudos

Hi,

I hve tried what you told ,but still no confirmation of qty.

wht might be the reason?

Regards,

pavan.

Former Member
0 Kudos

Hi there,

When no stock is confirmed in schedule lines, it means that stock is not there in the plant.

In MB1C, post the stock & then re-do availability check. It will propose the delivery scheduling & display confimed quantity in schedule lines.

Regards,

Sivanand

former_member204513
Active Contributor
0 Kudos

Dear Pavan,

Have you enter the delivering Plant in the sales order or not !!!

If not enter the plant then check,

I hope it will help you,

Regards,

Murali.

Lakshmipathi
Active Contributor
0 Kudos

Dear pavan

What you have seen is correct. It is bcoz stock is not available to confirm in sale order for that material.

If you are trying to test in development server, create some stock in MB1C with 561 movement type and save. Now go to VA02, input the sale order and execute. There go to schedule line tab and do availability check.

thanks

G. Lakshmipathi