Dear Gurus

i got a problem with 'x' material,

Initailly for 'x' material they made po with Rs.100/- instead of Rs.10/- and GR/Miro also over. We found this mistake after material period is closed ie after 4 months. Then we modified the price throgh mr21, after that it took as Rs.10/-.

here the problem is.. through mc.9 since 4 months if from 04.2008 till 07.2007 material price is taken as Rs. 10/-. But in the month august it is showing material price is Rs.100/-.

After changing mr21 we did not change any price.

Now the price should be Rs.10/- How to do that.