Planning Activity quantities on Production cost centers

Former Member
0 Kudos

Hi,

I would like to enter plan quantities of activities to Direct Production Cost Centers. Unfortunately I cannot use automatic transfer of quantities from PP (KSPP) as we don't have LTP (long term planning) in production.

We are planning only sales quantities in KEPM in CO-PA and transfer these quantities to SOP. Then we run MPS and MRP.

If I cannot transfer planned activity types quantities from production automatically (KSPP) I would like to find a way how to obtain the number scheduled activities for the next year on work centers.

Is there any table or raport where I can check scheduled activities on work centers?

Regards,

Karol

Accepted Solutions (0)

Answers (1)

Answers (1)

srinivasa_maruvada
Active Contributor
0 Kudos

Hi

I am not sure....but check at TCode KS03 and enter your production cost centre and goto control tab and check Record Qty check box is selected or not.

Cheers