Usage Probability in MRP

Dear all,

I have a scenario described below.

Product M has demand 1000 qty.

After the mrp run, system will generate the requirement as below.

(Component) (On hand) (Usage Prob.) (Demand) (Requirement)

A 900 pcs 50% 500 0

B 100 pcs 30% 300 200

C 0 pcs 20% 200 200

My question is how to force system consume comp. A for all its stock - 900 pcs without manually revise the plnd. order.

and then consume comp. B with 100 pcs.