on 09-10-2008 8:14 AM
Hi
While adding component in Service order IW32,some of the components planned cost is not coming.When we see in item view,under costing relevancey-Not relevant to cost is coming as default and it is greyed out.
Upon further analysis,we found in MM03,MR4 view,under BOM explosion,if indiviual /collet filed is having 1 then cost is not coming in IW32.But if it is selected as 0 or 2,cost is appearing..
Can you tell us how this is related to cost...
Regards
Sudha
issue is closed by changing Mateiral master settings