production scheduler & profile configuration

Dear SAPper,

When i create production order, the production scheduler is automatically flled (ex.101) and then

the production scheduler profiles is automaticalled filled too.

I don;t maintain production scheduler & production scheduler profile in work scheduling in material master?

where did system pic thatt value??

Best regards,

Freddy Ha

Former Member
Former Member replied

Hi,

For your order type,

Please check if in OPL8 "Assignment" area - "substitute scheduler" field is defined.

This scheduler is picked up as default if not defined in material master.

If a PSP is attached to this defualt scheduler in OPJ9, then that will also be picked up in the order.

Hope this helps.

Regards,

Ashok