on 09-10-2008 8:11 AM
Dear SAPper,
When i create production order, the production scheduler is automatically flled (ex.101) and then
the production scheduler profiles is automaticalled filled too.
I don;t maintain production scheduler & production scheduler profile in work scheduling in material master?
where did system pic thatt value??
Best regards,
Freddy Ha
Hi,
For your order type,
Please check if in OPL8 "Assignment" area - "substitute scheduler" field is defined.
This scheduler is picked up as default if not defined in material master.
If a PSP is attached to this defualt scheduler in OPJ9, then that will also be picked up in the order.
Hope this helps.
Regards,
Ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It comes from the OPJ9 which is assign to you plant and scheduling profile in OPKP for your order typer at bottom of screen. Which is assign in OPL8 order dependent parameter.
Hope clear to you.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Sep 10, 2008 1:03 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.