Hi,

I created a vendor and I created Info record as a Subcontract and while I am creating the Purchase requisition I choosed the following things..

Purchase requisition standard after that I choosed the Item category is L( subcontracting) and I enter the Material ,Plant SLoc,quantity..etc..

And it showa the available vendos list Source of supply tab but the record is not saving it shows the error..That error is " Not possible to determine any components "

Could u plz give the suggestions for what I have to do to solve this error.

Thanks & Regards,

Sudheer

Accepted Solutions (1)

Accepted Solutions (1)

former_member335885
Active Contributor
0 Kudos

HI,

When you enter L as item category then there will be two icons which is displayed in the item detials Material tab. there you have a icon explode BOM and here you enter the child parts that make up the main part.

Thanks & Regards,

Kiran

Answers (3)

Answers (3)

kunal_ingale
Active Contributor
0 Kudos

hi

go to the po

in item level material tab at right side u will see components button

here give the components (raw material for for finished product)

or maintain bom for the fiinish product

in cs01 so system wildetect it automatically

regards

kunal

award if useful

Former Member
0 Kudos

Hi,

First create Components (BOM) for the Finished good in CS01 transaction and then try to create the PR for the Finished good.

Regards,

Narayana.

Former Member
0 Kudos

hi

Pls check have u maintained components for SFG in t,code CS01( Create BOM)

If not mainain the BOM for your material & then try again.

Regds

Edited by: BSA on Sep 10, 2008 12:37 PM