reservation blocking

Hi Gurus,

I'm not a PS responsible, there are some reservations blocking some materials on warehouse.those reservations are automatically created by the system for some projects, but altough projects are finished those reservations are not closed, so still blocking the materials. is there any completion flag or something like that to close that projects.

Thanks for your answers...

Edited by: ümit yavuz on Sep 10, 2008 8:57 AM

replied

Hi,

You can close the project in CJ20N. Open ur project and goto Edit->Status->Close->Set. If you know which activity has the reservation, you can close that activity only in similar way.

Regards

0 View this answer in context