on 09-10-2008 7:10 AM
Hi Everybody,
I have material called Generators which has to do services every 3 month . Vendor 'X' do his services at our premises.Whenever he do services he brings spare parts for Generator.My client want to record the spare parts.Can anyone how do you map it into SAP.
BR
govindaraj.d
welldone
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
U create a service PO first,
then u ask ur vendor wt spare parts r required first, then in the same PO u addin different line item if MMR is there otherwise give a short description & account assignmentcategory (consumption account) & save.
Then after service is done u do service entry sheet & GRN for spare parts
Pandari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
crate service po with acct asignment k and item cat d for the service using text ,in same po add the material used by vendor with acct assignment k so it will direct go to consumption
now do the service netry sheet in ml81n for the service item
and then gr for the material used
then do the miro wrt po or if u need diffrent invoice for service and material then do miro wrt po for material and wrt service entry sheet for service
hope it clears
regards
kunal
award if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai,
This scenario can be mapped by
1.Create the PO with both service Purchase & Cost center purchase.
2.In one line item, use item category D & acct assignment category K for services to be performed on Generator.
3.In second line item, use acct assignmnet category K for material spare parts purchase. Here enter the Dummy cost center in the PO - Item detail - acct assignment tab.
4.Release the PO, if release strategy applicable.
5.Create the service entry sheet by ML81N.
6.Do the GR for 2nd line item of PO.
7.Do the LIV for PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Create the Material & Service PO in one single PO.
Enter the spare parts which vendor replaces in the one line item with net price
In second line item enter the item category ' D" , Account category ' A' and short text, with AU as Unit of measure with Plant, system will ask for Service activity number and enter the number with Gross price & unit of measure per service number.
Save the PO , Do the MIGO for the Spare parts, stock will be update in plant
Do the Service entry sheet in ML81N for that service with same PO.
rgds
Chidanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you want to track the Spare parts you need to create the Material master.
Otherwise if you don't want to track the stock then you can do with the use Short text with Account assigned PO.
Here instead of creating the 2 PO ( one for Services & other for Materials)
You are creating the Single PO as vendor is same for both services & Materials
( Maintaining the material master is not mandatory here for Spare parts you can use Account assigned PO with Short text)
rgds
Chidanand
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.