on 09-10-2008 6:53 AM
Dear Experts ,
I have demand ready for next 3-4 months for some 60 materials . I can either go for MD61 but it will take time or build SOP plan and then transfer .
I want to ask whethere there is any T code or method ( may be export from XL sheet ) I can use for collective upload for demand .
Neal
Hi Neal,
For collective upload thro excel for MD61, you need to make an ABAP programme. It is possible.
We have implemented it ABAP made programme ZMD61 where the collective upload of PIR is done.
Take help of technical person and give your requirements.
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Neal,
There's no standard T code in SAP to fulfill your requirement.
Try out this,
In MD61,you can give some plan name and it will display the lists of materials in that particular
plant and you can fill the PIR's for the different materials for different months.
If this is not satisfactory,you can go for a customized T code ZMD61 and for this you have to prepare the
functional Specification and develop a T code where in you can upload the PIR's for Monthly or Weekly or
Daily requirements for more than one material.Again the drawback is anyhow you to fill the material code-->
Monthly requirement values,likewise instead of filling first in the excle sheet,then uploading try to use this
option plan in MD61.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.