can we do the schedule line based GRN if it is there please provide me configuration settings

regards

srinivas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

This is standard feature of SAP & does not require any customization.

In case of Scheduling Agreements, you can post GRNs based on Scheduling Lines only.

Prashant

Former Member
0 Kudos

Dear Prasanth

your right it is available in standerd sap

regards

srinivas

Answers (1)

Answers (1)

Former Member
0 Kudos

its possible with making RO with one line item.

regards

Former Member
0 Kudos

HI ramesh

HOW IT IS POSSIBLE PLEASE EXPLAIN IT TO ME WHAT IS RO

REGARDS

SRINU

kunal_ingale
Active Contributor
0 Kudos

hi

create SA in ME31L

maintain delivery shedule in ME38

then as per shedule do the grn

if the shedule date is not the gr date then system will give message as no item found

hope it clears

regards

kunal