cancel
Showing results for 
Search instead for 
Did you mean: 

How to connect two phases in the phases in one PI sheet. ?

Former Member
0 Kudos

Hi Gurus ,

I have created one control recipe for the one material . In which one operation & two phases are there. For the two phases different control recipe destinations are used.

But when i am creationg process order , two PI SHEETs are creating having same process order no for the two different phases.

My requirement in one PI SHEET both the phases should be included.

So please reply me .

Abhi

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hy Abhi,

Answer is already there in your Question itself.

For the two phases different control recipe destinations are used.

system will generates control recipe Control Recipe wise for a Process order.Meaning is if your Master Recipe / Process order contains 2 Control Recipe Destination then system will generates 2 Control Recipe.which contains the related PI category assign to that relevant phases.

So if You want only one control Recipe then you have to use only one Destination in your Master Recipe / Process order.

Regards,

Dhaval

Edited by: Dhaval Choksi on Sep 10, 2008 12:37 PM

Answers (0)