Freight in GRPO

Hi All,

One of my customer wans to include the freight cost in the item cost. But he wants to put the freight amount in header lavel. So that it will hit the freight A/C.

Thanks & Regards.

Santosh

Former Member
Former Member replied

Hi Santosh

If you want the item cost to be updated at header level, the distribution to row must be defined first under Administration > Setup > General > Freight > Distribution Method.

Kind regards

Peter Juby