Hi experts
I have some questions as following
1.can anyone explain the usage of indicator "Fix.Opr.Amt"? this indicator is in pm order operation general tab.
2. In background, I saw several place we can configure planner group. one in master data in plant maintenance->technical object->define planner group. another in maintenance plan->task list->general data
->configure planner group
I want to know the difference between the two configuration
thank you in advance!
hi
Planner group in task list is the one who is responsible for maintaining the task list.whatever you have specified here only reflect while creating the task list
whereas in technical object ,Planner group is called maintenance planner group is a group of employees planning and executing the task in plant
Also reg fix op qty you can view the sap help which is self explanatory
Indicator: fixed lot external processing
Indicator which specifies whether the externally processed operation is to be costed with or without regard to the lot size, that is, whether the costs for different lot sizes are the same or different.
Use
For plant maintenance:
If this indicator is set, the system does not take the execution factor into account.
The indicator fixed operation quantity is used primarily for sub-operations, whose superior operation has an execution factor, which should not be passed on to the sub-operation.
You can also use the indicator in the operation, if you want to prevent an execution factor in the routing being copied to a maintenance order.
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.