Dear all gurus,

The user wanted to re-trigger the PO release strategy upon the changes of the PO quantity (with values), however, the system is unable to trigger the release strategy again.

I've checked the following setting.

Original PO quantity = 10000 pcs

New PO quantity = 10020 pcs

PO output printed

Tolerance limit set to 10% (upper limit)

Release indicator set to "6-if new strat./value chg/outputted"

Is there any other other conditions/setting need to be checked in order to re-trigger the PO release strategy?

Thank you.

Regards,

Edwin