on 09-10-2008 2:07 AM
Hi guys,
I'm in the time schema, I'm near the end of the schema where I already have some Wagetypes in DZL:
i.e.
WT 2050 with 3.00 hours
WT 2500 with 8.00 hours
I need to minus the hours of 2050 from 2500 and store the result in 2500 back in DZL.
Basically my ZL end result should be
WT 2050 with 3.00 hours
WT 2500 with 5.00 hours
Any help would be appreciated.
Regards,
Kevin
Problem Solved.
In a previous rule I put the value of 2050 in VS.
VS has only 2 decimal points so I multiplied the value first by 100.
In the next PZL rule, when 2500 is current WT,
I did a
HRS=ENUM
HRS*100
HRS-K2050
HRS/100
ADDZL *
If anyone has a better solution, feel free to suggest
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.