Visibility of total Demand - Forecasted and Sales Order

Hi All Experts,

I am having another issue while visualizing Demand or Total Requirements.

We are having following scenario

(1) MTS with planned independent requirements (strategy 40)

(2) MTO : for Top Level Assembly with Sales BOM (strategy

50). Customer orders created for this, will net off

Forecast requirements.

For Components, MRP will generate requirements.

I want to have a report which will tell me the total Demand / requirements (Top level and components included) up to specific future period.

I have tried ME79 but this does not include Customer orders and also exclude past demand when all materials selected.

Is there any standard SAP Report / Table is available to get this information ?

Please advise ASAP as I am stuck here.

Thanks and Best Regards,

Mitesh Desai