I created a production order for the manual component with qty 10. Then issued 10. Then I try to change Planned Qty to 1 and get a message :

"planed qty is below than issued"

Can you please explain me what is a reason for this?

Thanks,

Olga

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Why is it?

Thanks,

Olga

jitin_chawla
Advisor
Advisor
0 Kudos

Hi Olga,

Please check the following explaination in the Document resource centre for the Production Bill :

Planned Quantity u2013 Enter the required quantity of the parent item to be produced. 1 is the default quantity for this field. You can change the quantity as long as the Production Order is still a Planned status. You can also change the quantity when the order is Released, however the quantity could not be decreased below the completed quantity of the parent item.

Hope it clarifies.

Regards,

Jitin Chawla

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Olga,

You can only change quantity to higher not lower when you have issued quantity already.