Im working with 2lis* extractor from Lo Cockpit, and i have the followings questions:

1)For example, im using 2lis_02_itm extractor:

  • I have filled the setup tables on 09.01.2008

  • On 09.05.2008 i have executed Initial Load from BI

Question:

Which is the situation for those records that were created between 09.01.2008 (after filled setup tables) and 09.05.2008 ?

2)For example, im using 2lis_02_itm extractor:

  • I have filled the setup tables,executed initial load and schedulen delta load for this extractor.Everything works fine.

  • After a while (for example 2 months) i need to add another extractor : 2lis_02_scl into the current Cube.

Question:

Do i have to filled again the setup tables in order to process the initial load for 2lis_02_scl ? or can i executed initial load from the old setup tables and the begins with delta load?

THANKS A LOT