Dear All,

I want to revaluate the planning Cost for this year. I have Created the Plan Revalution through Costomisation. Now when I want to revaluate the Planning Cost through T Code KSPU (Revaluate Planning Cost), it throughs an error "Incorrect Plan revaluations / Revaluation was not executed"

Is it necessary to do some more configuration for revaluation of Planed Cost?

Can any one guide on revaluation of Planned Costs.

Thanks and Reagrds,

Ramnath.

replied

Please configure a revaluation in KPU3 and give a percentage there.

The percentage by which you want to reevaluate the costs. Specify the cost element and cost centers you want to reevaluate.

You can reevaluate with different factors for different cost elements within the same cost center

Keep us updated on the progress....and let me know of any questions in the process

Thanks

Naveen