on 09-09-2008 4:05 PM
Hi experts
I have an issue related to sub-contracting.
Component 'A' is used to make materials B,C and D(at subcontractors end)
I have made a sub-contracting PO for material B and did transfer posting. I have consumed 50 % of the quantity of 'A' and made B material.
Now i want to make material 'C' by using the remaining component of 'A' at the sub-contractor's end.
How can i receive the material 'C' from sub-contractor because already i made sub-contracting PO for the material 'B' and sent the component 'A'.
Please suggest me a solution for this scenario.
Thanks & Regards
Bala
Hi All,
Thanks your valuable replies.
I have followed the steps as you mentioned.
what to do with the Open PO of the material 'B'. should i need to delete it?
I have done the reconsilation for the qty received against the PO.
Dear Kiran,
i can make 15 type of materials from the component 'A'. so i can't mention all the materials in the PO.
Thanks & Regards
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think you can do like below -
Create Subcontracting PO as
Sending Mat. (RM) Qty Receiving Mat (FG) Qty
A 5 B 1
A 3 C 1
A 2 D 1
While doing transfer point, you do in parts wise as first send only A with 5 den 3 den 2. In case of excess you can reverse through 542 then system remove the stock from subcontractor send to own stock.
Regards
Goutham
Hi,
Why do you have to make a seperate PO. incorporate both B and C in one Subcontracting PO and send material A propotionately between both the materials.
In case if extra stock is lying at the subcontractors end we can bring it back with the help of 542 Mvt Type.
Thanks & Regards,
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
U have to make another PO for C with the component as A. there is no problem if sufficient material is available to make the product at vendor place.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Make another PO for C with the component as A.
Stock at subcontractor is not linked to a PO. So you can consume stock against any PO.
Hope this resolves,
Lakshman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.