on 09-09-2008 3:08 PM
For Project and WBS elements, we activate the budget availability control in the budget profile and assign the budget profile to the Project. So once we budget one WBS elements under that project and release the project, the availability control is active for all WBS elemens under this project.
My question is whether we can turn off the availability control for one WBS element under that Project and let the availability control on for the other WBS elements under that project.
thanks,
Ting
Hello Ting,
I am afraid it is not possible. You can enable budget availability control in the budget profile or using transaction CJBV (Activate Availability Control) both of them at projecte level.
You should create the WBS in two separated projects, one with budget control enabled and the other with budget control disabled.
You could also play with cost element exception list, the cost elements in the list doesn't affect to the budget. The problem is you should use different cost elements for each WBS.
Hope it helps.
Regards,
Marc
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.