Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

cProjects-MS Projects Export - Role-Task assignment...

When I export from cProjects, I have data mismatch from cProjects to MS Project.

A task of 5 days is assigned to 3 roles:

Role 1 for 2 days

Role 2 for 1 day

Role 3 for 2 days.

However, in MS Project, the Role-Task-Assignment gets uniformly distributed across all tasks.

It shows:

Role 1: 1.67 days

Role 2: 1.67 dats

Role 3: 1.67 days.

Please suggest.

Thanks in advance.

Not what you were looking for? View more on this topic or Ask a question