Trigger point for rework operation

0 Kudos

Hi All...

Please clarify me....

I attached a trigger point for rework ope in routing. which will create ref op set. but at the time of confirmation I am giving the 50qty for yield and 25 for rework qty and status pcnf and saved, then system creating the ref op set , but it is picking the total qty from the previous ope.

where i want, system should pick from the qty from rework for the op qty..

please correct ...me ?

what is the std process for trigger point ...from where it will pick the qty??

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

Please note that if it is a operation which will get added in between the 2 operations, then system will default the qty as equal to the earlier operation. Hence you will get the same qty as the earlier operation. Hence you confirm the remaining qty of 25 in the operation and proceed for furthur operation.