where to chk the PipeLine process steps in BPM Scenario...

former_member182455
Active Contributor
0 Kudos

hi experts,

i hav a scenario where i need to send multile file formats to an synchronous R/3 system and from R/3 it needs to be forwarded to the Target system in file format... its a BPM scenario...

i need to CHK the sequence of Steps or Pipeline process to knw where exaclty the message is at each piont of time...

can any one help on this plz...

Thanks and Regards,

Srinivas

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

In saplogon check in SXMB_MONI

When the screen appears select your BPM scenario and when the new screen opens under the Graphic option click on graphical protocol.

You will be able to see the process graphically

Regards

Vijay

VijayKonam
Active Contributor
0 Kudos

SXMB_MONI_BPE or in SXMB_MONI, in your message look for PE and click on it. It will take you to the BPM monitoring. There select either graphical or technical views.

VJ

former_member183906
Active Contributor
0 Kudos

its possible to do the same using the ALERT Framework also...for the same pls go through the info provided below.

From SP 14 on PMI-free alerting was introduced. That means before SP 14 one has to configure and activate the End-to-End Monitoring, and to schedule the report SXMSALERT_PROCESS_DATA_GET in order to extract the alerts from the PMI data. For SP 14 and higher, that's not longer necessary.

If no alerts are being delivered, please check if "Suppress multiple alerts of this rule" is checked for your rule.

For SP 14 and higher you could also have a look at the report sxmsalert_logreader. This report shows some information about alerts being created or not.

You'll find more information about trouble shooting the alerting in SAP Note 913858.

Also just check if this batch program (RSALERTPROC) is running or not.

The links below on Alert Management (ALM) will be of good help to you:

http://help.sap.com/saphelp_nw04/helpdata/en/3f/567ddea69d3d4c93a6aedabd08899e/frameset.htm

http://help.sap.com/saphelp_nw04/helpdata/en/3f/81023cfa699508e10000000a11402f/frameset.htm

Also go through these blogs:

https://www.sdn.sap.com/sdn/weblogs.sdn?blog=/pub/wlg/1382. [original link is broken] [original link is broken] [original link is broken]

Meanwhile look at these forum threads also:

Also, In ALRTCATDEF, go to SETTINGS--> CONFIGURATION. By default, the option selected is INTERNAL PROCESSING. Select the option SMTP FORWARDING AS XML and give the email id. This will enable you to send an email alert whenever an error occurs in XI.

I hope it helps you in finding a solution to your problem.

Former Member
0 Kudos

Hi,

You can Check this in SXMB_MONI_BPE

For Sync Process, if you want to see the response in MONI means, u need to configure few parameters in SXMB_ADM

Regards

Seshagiri