We are facing following problem in MIGO -
A PO was created say for 500 Nos of a material X and first GRN was created say for 50 Nos which produced material document Y in MIGO.
When subsequent GRNs were created against the same PO, system has taken material document Y as reference for 4-5 subsequent GRNs.
Kindly suggest the solution
Regards,
Pawan Khurana
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In MIGO if you choose GR against Purchase Order and do GR for partial quantity and subsequently the user might have choosen Subsequent Delivery against Material document in which the first GRN was selected the system will propose GR for balance quantity .There is nothing wrong with that as ultimately all GRN will be reflected against the same PO.
Dhruba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.