Changing Price Control from S to V with Material ledger active

Hi,

I would like to change price control for particular materials from S to V. However, I have Material Ledger active and these materials have Price Determination set as "3" (single and multilevel).

Is it possible to change price control indicator for these materials from S to V and which steps should be made to achieve this.

Some of these materials have stock and movements registered in Material Ledger in previous periods, and some of them have zero stock. Will there be a problem for the materials with movements posted?

The materials I want to modify are not used in production, and therefore I don't need multilevel rollup of variances.

Best regards,

Karol

Edited by: Karol on Sep 9, 2008 10:02 AM

replied

Hi Karol,

No problem for materials without stock. Indeed it isnu2019t a problem for materials with stock either, as long as you do not intend to switch back to S3 again.

But I would advise to ensure that you are either on a relative high SAP_APPL level or check for CO-PC-ACT SAP notes relating to CKMM as there where some program bugs that prevented the deletion of all ML data when a material is switched from S3 to V2.

Regards

Karl