Project team assignment issue

Former Member
0 Kudos

Dear All,

when i am trying to attach person with a particular wbs element,

i am getting one message " no person can be assigned for that duration" altough the basic start and finsh date is maintained properly.

can nybody look into the matter??/

thnx in advance

ashis

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please go through SAP note- 543362

Thanks

Former Member
0 Kudos

thanx dear, as the note is quite informative,

but dere is not much about assigning person to WBS elements, rathet its about assigning person to activity and work force plannig......

can u pls. through some light on specially assigning the person to WBSand why the error is coming like " No person can be assigned from period x to period y"

thanks

ashis

Former Member
0 Kudos

While assigning the person ensure to check the availability of the employee. System will check if the current date is in range of start and end date ofemployee.

Regards

Sreenivas

Former Member
0 Kudos

thanx a lot

regards

ashis