Project team assignment issue

Dear All,

when i am trying to attach person with a particular wbs element,

i am getting one message " no person can be assigned for that duration" altough the basic start and finsh date is maintained properly.

can nybody look into the matter??/

thnx in advance

ashis

Former Member
Former Member replied

While assigning the person ensure to check the availability of the employee. System will check if the current date is in range of start and end date ofemployee.

Regards

Sreenivas