Project Stock to Sub-Contractor (Mb1B-541Q)

Former Member
0 Kudos

Hi,

In the business process , we want to transfer project stock to subcontractor (MB1B 541Q) .

But in current setting , it's not supporting.

Shall apperaciate some soluation on this process.

Regards

Shyam Kogta

Accepted Solutions (1)

Accepted Solutions (1)

hnmuralidhara
Active Contributor
0 Kudos

Dear Shyam,

This is possible after modification in your customization settings;

(a) Logistics general / Tax on Goods Movements / India / Business Transactions / Subcontracting / Maintain Move type Groups.

(b) Modify Screen Layout using transaction code OBJJ

Steps during day-to-day transactions;

(a) Create a PO using Account Assignment Category "Q"

(b) You have to create one more PO for Semi-Finished material for components

(c) Make goods receipt against 101Q

(d) Transfer this stock using movement type 311Q using WBS element

(e) Create S/C Challan if it related to Indian Excise

(f) Make Goods Receipt of Semi Finished material

Explore following URL

http://help.sap.com/saphelp_dimp50/helpdata/EN/4d/2b90b043ad11d189410000e829fbbd/content.htm

Bye and all the best!!

Muralidhara