Fixed Cost in Activity Type

Hi all

I have assigned the fixed cost to an activity type for entire fiscal year.

when i running the cost estimation the system is calculating the acitivity cost including of the fixed cost.

I want to capture the fixed for the period and not for the no of unit produced.

Eg:

Fixed cost : 25000

Variable cost :0.5/hr per unit.

BOM unit : 10 hrs

when i execute the cost estimation the system is calculating the amount as 25005 ( 2500010) +(0.510)

which is a wrong calculation.

Can anyone guide me how to achive this.

Regards

SAP4ME