Dear Experts

As per our costing requirment,they want to valuate materials based on certain parameter like count in Textile industry,

suppose we are putting 100rs.mtr &

if we are using 60s count yarn price should pick 25%

if we are using 80s count yarn price should pick 50%

For this activity to be done,We want costing relevancy in BOM & Routing to be activated by percentages.

But option is not working in our client,shall we have do any customisation for that.

Regards

Sandeep

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can use variant configuration for this requirement.

Ask your PP guy and he will tell you the flexibility that you have in variant configuration and the lenght and breadth of features it offers.

Your scenario is perfect fro variant configuration.

All the best.

Answers (1)

Answers (1)

former_member184655
Active Contributor
0 Kudos

Dear Sandeep,

For individual BOM Components you can decide whether its relevant to 100% costing or 50 %.

But in the routing for individual operation I dont think it's possible to set its 100 % relevant to costing or 50

% relevant to costing.Either you can set its relevant or ir-relevant.

For BOM,after assigning the BOM components,select a single component (Row),then press F7---->Click

on Status/Long Text tab key->there you can see costing relevancy->select one from the option.

Also check the configuration setting in T code OS18.

Regards

Mangalraj.S

Former Member
0 Kudos

Dear mangal Raj

The problem we are facing is for Costing Variant-ppc3 we are able to get percentage wise costing,but for PPC1 (standard cost estimate we are not able to get this percentages.

how to make active for PPc1 variant.

Regards

sandeep

Former Member
0 Kudos

Dear mangal Raj

Please provide how to activate in customisation setting,

.

Regards

Sandeep

Former Member
0 Kudos

Dear all

whats the imp of Orgin Group,is there any relation for this to Update Costing relevancy.

Regards

sandeep

Former Member
0 Kudos

Hi Sandeep,

We are facing the same problem i could see the effect of costing relevancy in PPC3 but not in PPC1.Did you find any solution to this problem why it's happening?